9-13-22
9-13-22
9-13-22: A look inside
9-13-22: A look inside
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Masonry work continues for new restrooms
9-13-22: Masonry work continues for new restrooms
9-16-22: Exterior painting
9-16-22: Exterior painting
9-16-22: Exterior painting
9-16-22: Exterior painting
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Cutting rebar
9-22-22: Cutting rebar
9-22-22: Smoothing concrete
9-22-22: Smoothing concrete
9-22-22: Concrete hardener is spread on the newly leveled concrete
9-22-22: Concrete hardener is spread on the newly leveled concrete
9-22-22: Several new pieces of HVAC equipment await being lifted to the roof
9-22-22: Several new pieces of HVAC equipment await being lifted to the roof
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-13-22
9-13-22
9-13-22: A look inside
9-13-22: A look inside
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Rebar for new flooring
9-13-22: Masonry work continues for new restrooms
9-13-22: Masonry work continues for new restrooms
9-16-22: Exterior painting
9-16-22: Exterior painting
9-16-22: Exterior painting
9-16-22: Exterior painting
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Concrete is pumped in place for the new plant floor
9-22-22: Cutting rebar
9-22-22: Cutting rebar
9-22-22: Smoothing concrete
9-22-22: Smoothing concrete
9-22-22: Concrete hardener is spread on the newly leveled concrete
9-22-22: Concrete hardener is spread on the newly leveled concrete
9-22-22: Several new pieces of HVAC equipment await being lifted to the roof
9-22-22: Several new pieces of HVAC equipment await being lifted to the roof
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-22-22: HVAC equipment is crane-lifted to the rooftop
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected
9-27-22: Fire protection piping is connected